Construction planning

Environment

InterDC datacenters are environment friendly datacenters. Meaning that we use renewable energie and we use the temperature of the outside air to cool our datacenters.

Construction planning

The InterDC datacenter will be build in 3 construction phases:

Phase1:
Datafloor with 20 racks
Power: Ups System, Single feed
Fireprotection: Co2 extinguishers
Cooling: Free Air koeling & Uniflair airco
Fiber: Single fiber
Expected completion date: 30 june 2011
Status: Ready

Phase2:
Datafloor with 40 racks
Power: UPS system, A+B feed
Fireprotection: Vesda system, CO2 extinguishers
Cooling: Free Air koeling & Uniflair airco
Fiber: Single fiber + Backup
Expected completion date: 31 december 2011
Date of completion: 25 june 2012
Status: Ready

Phase3:
Datafloor with 60 racks
Power: UPS system (N+1), A+B feed, generator
Fireprotection: Vesda system, CO2 extinguishers
Cooling: Free Air koeling & Uniflair airco
Fiber: 4 geographical redundant fibers
Expected completion date: 31 march 2014
Date of completion: 25 january 2016
Status: Ready

When phase 3 is completed, InterDC will be certified as Tier3 datacenter.

Datacenter Enschede
  • InterDC Enschede Haven
  • Josinkstraat 30
  • 7547AB Enschede
  • The Netherlands
Datacenter Enschede
  • InterDC Enschede Marssteden
  • Marssteden 110
  • 7547TD Enschede
  • The Netherlands
Datacenter Hengelo
  • InterDC Hengelo
  • Sherwood Rangers 1
  • 7551KW Hengelo
  • The Netherlands
Datacenter Doetinchem
  • InterDC Doetinchem
  • Gildenbroederslaan 1
  • 7005BM Doetinchem
  • The Netherlands