Construction planning

The InterDC datacenter will be build in 3 construction phases:

Phase1:
Datafloor with 20 racks
Power: Ups System
Fireprotection: Co2 extinguishers
Cooling: Free Air koeling & Uniflair airco
Expected completion date: 30 juni 2011
Status: Ready

Phase2:
Datafloor with 40 racks
Power: UPS system and generator
Fireprotection: Vesda system, CO2 extinguishers
Cooling: Free Air koeling & Uniflair airco
Expected completion date: 31 december 2011
Status: In progress

Phase3:
Datafloor with 60 racks
Power: UPS system (N+1), generator (N+1)
Fireprotection: Argon gas system, Vesda system, CO2 extinguishers
Cooling: Free Air koeling & Uniflair airco
Expected completion date: 31 september 2012
Status: Waiting