Construction planning

Carrier-neutral

InterDC has an open network policy, which means that any internet/network provider can establish themselfs in our datacenter. This gives you the option to choose from a broad selection of internet/network providers within our datacenter.

Construction planning

The InterDC datacenter will be build in 3 construction phases:

Phase1:
Datafloor with 20 racks
Power: Ups System, Single feed
Fireprotection: Co2 extinguishers
Cooling: Free Air koeling & Uniflair airco
Fiber: Single fiber
Expected completion date: 30 june 2011
Status: Ready

Phase2:
Datafloor with 40 racks
Power: UPS system, A+B feed
Fireprotection: Vesda system, CO2 extinguishers
Cooling: Free Air koeling & Uniflair airco
Fiber: Single fiber + Backup
Expected completion date: 31 december 2011
Date of completion: 25 june 2012
Status: Ready

Phase3:
Datafloor with 60 racks
Power: UPS system (N+1), A+B feed, generator
Fireprotection: Vesda system, CO2 extinguishers
Cooling: Free Air koeling & Uniflair airco
Fiber: 4 geographical redundant fibers
Expected completion date: 31 march 2014
Date of completion: 25 january 2016
Status: Ready

When phase 3 is completed, InterDC will be certified as Tier3 datacenter.

Address
  • InterRacks C.V.
  • Joskinstraat 28
  • 7547AB Enschede
  • Nederland
Datacenter
  • InterDC
  • Joskinstraat 30
  • 7547AB Enschede
  • Nederland
Bank info
Bank: ING
City: Enschede
Country: Nederland
IBAN: NL11INGB0004893569
BIC: INGNL2A
Chamber of commerce
Chamber of commerce: 08135503
Region: Veluwe en Twente
Vat number: NL8147.47.796.B01