Tuesday 28 June 2011
After 2 days of hard work, our datacenter is now cooled by a new Uniflair downflow cool unit. For the new Uniflair airco we needed to place some chillers on the roof.
Friday 17 June 2011
After 2 weeks of comparing cooling solutions we finally decided to go for the downflow cooling (with the free air cooling option) from Uniflair.
The units are ordered and will be arriving within the next 2 weeks.
Wednesday 1 June 2011
With a cooling specialist we looked at the possible cooling solutions for our data-center.
Tuesday 31 May 2011
The security cams are placed (inside and outside of the building).
Friday 27 May 2011
The first server has been placed in our datacenter. This means that the datacenter is almost ready, and more servers will be placed soon. The construction phase of the datacenter is almost complete.
Saturday 21 May 2011
The power grid is ready for use. The first 10 racks have each its own 16 ampere group with kWh meter.
Wednesday 18 May 2011
The fiber connection to Amsterdam is Ready. Starting today we can use the new connection between Globalswitch (Amsterdam) and Interdc (enschede).
Thursday 12 May 2011
The build of the new walls for the data-room has been started. Also we are going to place a new wall against the existing brick wall. This is necessary because the brick wall is not completely dust free and not usable for a data-room.